Turnkey Project Process:
From Inquiry to Installation | RUN-TECH
Here is the turnkey project process at RUN-TECH, from your first enquiry to the day your line runs: eight stages, each with a named deliverable and a clear action for you. Buyers who assemble a line from several vendors know the failure mode. Between machines nobody owns the seam, and a missed handoff becomes your production delay. Before 2025 our main market was domestic, with customers including Unilever, Nutrich, Rainbow, REDLION, BLUE MOON and SUPER, and machines sent overseas went through trading companies. Since the end of 2025 we have built the direct process below. This page opens the sequence so you can see what happens, what you receive and what you must prepare. Figures that depend on your site, your product or your destination are confirmed with the quotation once those details are known.1. The Eight Stages at a Glance
A turnkey packaging project runs through eight stages, each with a named deliverable and a clear action for the buyer. The sequence covers requirements, 3D layout and quotation, a sample trial, in-house manufacturing, a 24-hour FAT, export packaging, installation and training, and permanent after-sales support.
The table below is the short version; each stage then follows the same input, we do, you receive structure. Use it as a checklist when comparing suppliers, because a turnkey quotation is only as good as the handoffs behind it.
Stage | What you receive | Your action |
1. Requirements and samples | Confirmed requirements checklist and a named technical contact | Send bottle and cap drawings or samples, product, target output, voltage and floor area |
2. 3D layout and quotation | 3D line layout and a detailed quotation within 24 hours | Confirm scope, model mix and floor plan |
3. Sample trial | Video trial report on your own product and a compatibility analysis | Approve the configuration before any metal is cut |
4. Manufacturing | Build records, material confirmation and access to a factory audit | Optional: audit the two Changzhou bases |
5. FAT | FAT protocol, trial report and video, contact-material confirmation, final inspection record | Agree the acceptance criteria in advance |
6. Export packaging and shipment | Packing list and shipping documents, wear-parts stock recommendation | Nominate the consignee and confirm destination documents |
7. Installation and training | A running line, a trained operator team and the machine documents | Prepare site, utilities, access and people |
8. After-sales | Remote fault diagnosis, source-direct spare parts, 18-month warranty cover | Report the fault with a description or grant remote access |
Stage 3 gates stage 4: fabrication starts only after you approve the configuration that passed the trial. That keeps a project from drifting into an argument about whether the machine could ever run your product.
2. Stage 1: Requirements and Sample Submission
3. Stage 2: 3D Line Layout and Quotation Within 24 Hours
4. Stage 3: Free Sample Trial and Compatibility Report
5. Stage 4: Building Your Line in Changzhou
6. Stage 5: 24-Hour FAT on Your Own Bottles and Liquid
7. Stage 6: Export Packaging and Shipment
8. Stage 7: On-Site Installation, Commissioning and Direct Training
9. Stage 8: Permanent After-Sales and Source-Direct Spare Parts
10. Certification and Documentation
RUN-TECH holds ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015 certification. Each covers a defined area: quality management, occupational health and safety, and environmental management respectively. The useful question for a regulated buyer is which document covers your configuration, so ask for the certificates applicable to your model and we will send them with the quotation.
On CE marking, we work machine by machine. A machine can be supplied with its own CE certificate, issued at the customer's request. Ownership belongs to the customer and we do not retain it; the document is made for your configuration and stays with you. The governing text is the EU Machinery Directive 2006/42/EC, which sets the essential requirements. Certificate numbers and issuing bodies are supplied with the quotation for your model.
11. Five Commitments We Put in Writing
Five items define the commercial side of this turnkey project process. All of them can go into the official agreement.
Commitment | What it means in practice |
Quotation | Professional, detailed and competitive, with the configuration and documents identified |
Installation and training | On time and on site: installation, commissioning, direct operation and training |
After-sales service | Permanent and on time, with remote diagnosis and source-direct spare parts |
Warranty | 18 months on the machine |
Lead time | Typically 15–30 days for a standard single machine and 30–45 days for a complete line |
We keep this table short on purpose: a buyer needs terms they can hold a supplier to. Payment structure and milestones are agreed per project and set out in the contract.
12. What You Prepare, and What We Document
A turnkey project moves at the speed of its slowest input.
You prepare | We handle |
Bottle and cap drawings or physical samples, plus a little product | 3D layout, configuration and detailed quotation |
Target output, product viscosity and chemistry | Sample trial, video report and compatibility analysis |
Site utilities, floor area and access route | In-house fabrication, assembly, wiring and programming |
Operators and one acceptance owner | FAT, export packaging and shipping documents |
Destination-market documentation requirements | Installation, commissioning and direct operator training |
Figures we keep off a public page — installation days, engineers on site, response-time commitments, certificate numbers and issuing bodies, workshop floor area, and the CNC machine list with brands, models, axis counts and machining tolerances — are confirmed per project and available for inspection at audit. None is secret; the equipment and inspection records can be seen there, and the applicable terms go into the agreement.
Let's Connect
Have your bottles and product ready? Send us your samples and we will run a trial on your own liquid, then return the video report and a 3D layout with quotation. Contact RUN-TECH to send samples and start your turnkey project — tell us your target output, voltage and floor area, and we will take it from there.